SIMM Inspection Job Sheet
Structural Inspection and Maintenance Management
Inspection Details
- Inspection Date
- 2023-11-15
- Inspector
- John Doe
- Accompanied By
- John Doe
- Document No
- SIMM-JS-2023-001
- Project
- North Pit – Sector 4 Conveyor Upgrade
- Client / Site
- Tronox
Observations and Findings
Reference
REF-7821
Action Type
Structural Repair
Item Description
Main support beam for conveyor CV-04
Functional Location
Conveyor Support - CV-04-SUP-02
Category
Priority
Condition Description
Visible corrosion on lower flange with ~15% material loss. Surface pitting along entire length.
Required Action
Clean exposed rebar; apply corrosion protection; use wet-to-dry epoxy; reinstate with concrete repair. Complete within next 12 months to limit further degradation.
Photo Documentation
#1.2 [C3, P3] Moderate Corrosion